Construction Progress
[Municipal Building Construction Index]

Mid-May 2002

Finishing the foundation.


b502.jpg (73712 bytes)

b533.jpg (45547 bytes)

b539.jpg (44102 bytes)

b540.jpg (55969 bytes)

b541.jpg (73330 bytes)

b544.jpg (32306 bytes)


b504.jpg (62456 bytes)

b513.jpg (67049 bytes)

b514.jpg (28718 bytes) 

b526.jpg (36273 bytes)



Municipal Complex, Senior Citizens Center & Public Library

Hasbrouck Heights Free Public Library
Free Public Library [Dedication] [Mayor's Remarks] December 14, 2003
[Photos of the Library's big move] November 17-18, 2003

New Municipal Complex Dedication  October 18, 2003
[Boro Hall Ribbon Cutting]    [Senior Center & Prayers]    [Remarks by Mayor Torre]
[Photos] Employees "Raising the Flag" at New Boro Hall on September 12, 2003
[1st Mayor & Council Meeting] in the new chambers, September 9, 2003
The Big Move -- September 5, 2003.  Take a tour of the New Municipal Complex
[Moving into Municipal Offices][Library & Senior Center][Library Big Room][Basement]

Mason's Cornerstone Ceremony, March 2, 2003 [Story & Program] [Ceremony]
Municipal Complex Ground Breaking Ceremony, October 13, 2001 [Photos]

Webcam          The Big Fire [Index]      Library & Senior Center [Background] info


Photos of Construction Progress

Late April 2003 -- to come
Late March 2003 -- to come
Early March 2003 -- to come
Late January 2003 -- to come
Mid-December -- to come
October 2003 -- to come
Late September Council Tours Site  -- [First & Second Floor] [Basement & General Site]
Late August -- [2nd floor & start insulation][1st floor & basement][Start roof][General site]
Early July 2002 -- Pouring concrete floors  [Second floor] [First floor]
Late May/Early June  -- Working the Steel [#1] [#2] [#3]  Working Steel Progression
Mid-May -- Finishing foundation work.
Late April 2002 -- Pouring foundation walls for back of building
Early April 2002 -- Pouring foundation walls for front of building
Late March 2002 -- Completing excavation & starting foundation.
February/March 2002 -- Beginning excavation.

Site Preparation
Boulevard Shell Demolition April 16, 2003 [Group 1][Group 2]
Old Bank Building demolished [Photos]      Apartment Building demolished [Photos]
Houses demolished September 17 & 18, 2001 [Photos 1][Photos 2]
Houses demolished January 10, 2001 [Photos 1][Photos 2]
Begining the process [Photos]

Working plans 90% complete --  prior to excavation
Floor Plans: [Basement] [First Level - Municipal Offices & Senior Center]
[Second Level - Library] [Park Area at Boulevard & Madison]
Elevation: [Front - Boulevard] [Back] [Madison Ave.] [Central Ave.][Treatment Enlargement]
Architect's Drawing & model as posted at Boro Hall, March 2002

BAR_ELEG.GIF (11170 bytes)




Please patronize our sponsors. Ads with links are clickable.

BAR_ELEG.GIF (11170 bytes)

news, information and features  LOGO.GIF (7473 bytes) tm

Home Page   ·   Site Map   ·   teterboro-online.com
The Gazette Newspaper   ·   The-Boulevard-Mall

Thank you for visiting our hometown.  Come back soon!
[Contact Webmaster] [Policy Statement] [Advertising information]   Copyright 1998-2008. All rights reserved.
All photographs used in this web-site are copyrighted and property of the photographer.
Photographs used herein are on loan and are not public domain 

BAR_ELEG.GIF (11170 bytes)


Please patronize our sponsors. Ads with links are clickable.